Petites annonces | Enchères au Québec | Appel d'offres | Emplois | Circulaires | Nos Hebdos | Interurbain | Rencontre en ligne | Weblocal
Courrier Laval
Pool hockey résultats
Envoyer ce texte à un ami Imprimer cette page Réagissez à cet article

Completing the last phase

par Nathalie Villeneuve
Voir tous les articles de Nathalie Villeneuve
Article mis en ligne le 29 avril 2007 à 13:00
Soyez le premier à commenter cet article
Completing the last phase
Much like earlier dry runs (this one involving Premier Jean Charest and Mayor Gilles Vaillancourt), the simulation exercise for the Laval Metro lasted 41 days. (Photo: Martin Alarie)
Completing the last phase
For the past several weeks, Orange Line trains have been crossing onto Laval island under the Rivière des Prairies, stopping at Cartier, Concorde and Montmorency stations. These dry runs simulated most conditions in real time, lacking only the major detail of ‘passengers’. Other than that, the runs constituted the last piece of the transport puzzle to be completed for the official opening date of April 28, 2007 more than two months ahead of schedule.
This last preparatory phase lasted 41 days, according to Daniel Choquette, assistant to contract administrators at the Metropolitan Transport Agency (AMT). The dry runs were intended to test the crossing times of trains and the patterns of arrivals and departures at the new stations under the central management of the Montreal Metro, explained AMT spokesperson Mélanie Nadeau.

The trains going back and forth between Montreal and Laval these past weeks were not the first to roll on the tracks, having been preceded by trains that were part of reduced-speed trial runs held for the past couple of months. The aim of that exercise launched in December of 2006 was to test the 15,000 networks of the system, with signals coordination getting top priority.

The value of these simulation exercises became clearly evident during one of these recent daily tests, when a minor derailment occurred, necessitating some adjustment to the faulty track which had been placed at a curve deemed much too sharp for the trains to handle effectively.

The simulation and dry runs of the Laval Metro took four months to complete – from December 2006 to end of April 2007.

(Photo: Martin Alarie)

Ces articles pourraient également vous intéresser

Vos commentaires

Nom complet:
(requis)


Adresse courriel:


Vos commentaires :
(requis)


Svp inscrire le mot affiché ci-dessus Impossible de lire le mot?

Svp inscrire le mot affiché ci-dessus:


Chez nos voisins


La question du net

  • Utiliserez-vous les services d'Opération Nez rouge?
  • Oui
  • Non

Liens